When will the I-495 Express Lanes extension open?
It is open. The 495 Express Lanes extension to the George Washington Memorial Parkway, near the American Legion Bridge, opened on Sunday, November 23, 2025, ahead of the contract schedule, and its 2.5-mile trail opened June 27, 2026 (VDOT). VDOT’s project page said full completion was expected in mid-2026, and it had not posted a final completion date when we checked on October 16, 2026.
When will the new American Legion Bridge be built?
No date is announced. Maryland’s 2024 federal grant application said the new bridge and toll lanes would be open to traffic by 2033. The project then restarted as a public-private partnership after a January 15, 2026 agreement between the U.S. Department of Transportation and Maryland, and no new date has been posted (checked October 16, 2026).
Will the 95 Express Lanes run both ways?
That is the plan, if it is approved. The Express Lanes operator proposes two-way lanes open at all hours over about 45 miles from Springfield to Spotsylvania, with about 140% more capacity, and says financial close would come in 2029 if approved. FFXnow reported on September 25, 2026 that VDOT told Fairfax supervisors construction could take place in the early 2030s. No completion date is announced.
When will the Richmond Highway BRT open?
Fairfax County’s timeline, updated October 2026, puts the start of bus service in fall 2033, after construction from spring 2028 to spring 2033. That is later than the 2031 start the FTA listed with information as of May 2024. The line runs 7.4 miles on Route 1 from Huntington Metro to Fort Belvoir, with buses every 6 minutes at rush hour.
When will VRE run on weekends?
VRE says it plans its first-ever weekend and late-night service once the Long Bridge project and other work on the line are done. VPRA puts the Long Bridge’s completion in 2030 (December 1, 2025). VRE has not announced a start date for weekend trains.
When will the Fairfax County Parkway widening be done?
VDOT says mid-2027 for both sections between Route 123 and Route 29, about 6 miles from four lanes to six. The Popes Head Road interchange in the middle is due in late fall 2026. The 45 mph work zone between I-66 and Route 123 stays until the widening is done (VDOT, checked October 16, 2026).
When will the Route 7 and Route 690 interchange in Purcellville be finished?
Loudoun County gives substantial completion in winter 2029, after construction that started in winter 2026. The county says it will cut traffic in downtown Purcellville and on Route 287.
Is Route 1 in Crystal City becoming a boulevard?
Not yet. VDOT’s study recommends turning the raised Route 1 freeway between 12th Street South and 20th Street South into a street-level urban boulevard, but it set no design or construction dates (page updated August 5, 2026).
When will the Duke Street bus lanes be built?
The City of Alexandria expects final design in spring 2027 and permits by mid-2027, with construction shortly after (page updated April 27, 2026). NVTA’s project dashboard gives the anticipated completion as December 31, 2029.
Is I-66 inside the Beltway HOV-2 or HOV-3?
HOV-3. Since December 5, 2022, a carpool needs three or more people to ride I-66 inside the Beltway free at rush hour, with an E-ZPass Flex set to HOV mode; before that it was two (VDOT). The same three-person rule applies on the 495 and 95 Express Lanes.